Sample Exam Questions

1.      EPA requires signers of the NOI to retain site inspection reports as part of the SWPPP for at least:

  • a)      One year from the date that the permit coverage expires or is terminated.
  • b)      Two years from the date that the permit coverage expires or is terminated.
  • c)      Three years from the date that the permit coverage expires or is terminated.
  • d)     There is no requirement.

2.      EPA expects inspections to include areas used for storage of hazard waste materials.

  • a)      True
  • b)      False

3.      There is no EPA requirement for signing inspection reports.

  • a)      True
  • b)      False

    4.      Which BMP will remove the least amount of sediment in runoff waters?

  • a)      A properly installed silt fence barrier placed at the toe of a hill.
  • b)      A properly designed and installed sediment basin.
  • c)      A rock barrier placed around an area (a.k.a. catch basin) drain.
  • d)     A straw bale barrier placed in front of a curb opening.

    5.      Clay soils are more erodible than silt soils

  • a)      True
  • b)      False

6.   Which one of the following best represents a definition of sediment?

  • a)      Displacement of soil particles by wind or water.
  • b)      Suspended soil particles found in runoff waters.
  • c)      Deposition of soil particles.
  • d)     None of the above.

7.    When inspecting for planting of seed, it is important for an inspector to determine if:

  • a)      A seedbed has been properly prepared.
  • b)      Information on the bag seed tags meet required specifications.
  • c)      Proper seed planting equipment is used.
  • d)     All of the above.

    8.      When inspecting a sediment basin, the most important item to inspect is:

  • a)      Ensuring water is always in the structure.
  • b)      The embankments are established in vegetation.
  • c)      The outlet structure releases water at the designed rate.
  • d)     Only clean and sediment free waters discharge from the system.

    9.      Less wind erosion will occur when the bare ground is rough. 

  • a)      True
  • b)      False

10.  An inspector needs to conduct a site inspection on an active construction site:

  • a)      Daily during the rainy season.
  • b)      At least once every 14 days.
  • c)      Monthly when drought conditions exist.
  • d)     As specified in the SWPPP.