June2010LogoCISECwhitebackground.jpg

Home
CISEC, Inc. - Who are we?
Find a CISEC (Revised with Towns)
Becoming a CISEC Instructor
United States Training and Exam dates
Canada Training and Exam Dates
Payment and Exam Application Forms and Exam Retake Form
Minimum Qualifications for Exam
Training Modules
Proctoring of Examination
Study Guide
Sample Exam Questions
Answers to Sample Questions
EPA's CGP and EGL Final Rulings and Sample Inspection Form
Certification Renewal/Replacement Contract/Replacement Certificate
Newsletters
CISEC Manual
CISEC Shirts and Stickers
Board of Directors Only
Instructors Only
Contact Us

Sample Exam Questions

1.     EPA requires signers of the NOI to retain site inspection reports as part of the SWPPP for at least:

a.      One year from the date that the permit coverage expires or is terminated.
b.     Two years from the date that the permit coverage expires or is terminated.
c.      Three years from the date that the permit coverage expires or is terminated.
d.     There is no requirement.

2.     The 2008 CGP requires the recording of rainfall amounts on an inspection report only when 1/2-inch or more of precipitation occurs.

a.      True
b.     False

3.     When a BMP is deemed inadequate, an inspector must always mandate a specific replacement BMP.

a.      True
b.     False

4.     Which BMP will remove the least amount of sediment in runoff waters?

a.      A properly installed silt fence barrier placed at the toe of a hill.
b.     A properly designed and installed sediment basin.
c.      A rock barrier placed around an area (a.k.a. catch basin) drain.
d.     A straw bale barrier placed in front of a curb opening.

5.     Clay soils are more erodible than silt soils.

a.      True
b.     False

6.     Which one of the following best represents the definition of sediment?

a.      Displacement of soil particles by wind or water.
b.     Suspended soil particles found in runoff waters.
c.      Deposition of soil particles.
d.     None of the above.

7.     When inspecting for planting of seed, it is important for an inspector to determine if:

a.      A seedbed has been properly prepared.
b.     Information on the bag seed tags meet required specifications.
c.      Proper seed planting equipment is used.
d.     All of the above.

8.     When inspecting a sediment basin, the most important item to inspect is ensuring:

a.      Water is always in the structure.
b.     The embankments are established in vegetation.
c.      The outlet structure is not clogged with debris.
d.     Only clean and sediment free waters discharge from the system.

9.     Saltation accounts for more soil loss by wind when compared to suspension.

a.      True
b.     False

10. According to the 2008 CGP, an inspector must conduct a site inspection on an active construction site:

a.      Daily during the rainy season.
b.     At least once every 14 days.
c.      Monthly when drought conditions exist.
d.     As specified in the SWPPP.

Click here to see answers to the above questions.

CISEC, Inc. PO Box 188 Parker, CO 80134

Phone: (720) 235-2783 Fax: (303) 841-6383